Power sector

  • Localization:Elektrociepłownia Elbląg – Energa Wytwarzanie
  • Range:

    Project of lifting elements of the "ECO tower" in the heat and power plant in Elbląg. Participation in the modernization of the biomass boiler together with the auxiliary construction project and the traverse project.

  • Realization:

    2018

  • Additional information:
  • Localization:Elektrownia Jaworzno – construction of a power unit J910
  • Range:

    RangeThe design of the assembly of the flue gas duct using hydraulic cylinders with a mass of approx. 300t along with the design of an auxiliary construction of windbreaks.

  • Realization:

    2017-2018

  • Additional information:
  • Localization:Elektrownia Turów – PGE
  • Range:

    The concept of installation of channels. Installation using A-LIFT travers.

  • Realization:

    2017

  • Additional information: